Project details

EPC project for three new switchboard shelters, complete with 11kV, 33kV and LV boards in GC2A, Gc3 and GC4 remote stations in Sarir

Libya

 

New Switchboard shelters in Sarir

Erection and finishing of substation building

 

New Switchboard shelters in Sarir

Installation connection site commissioning and protection tests of 11kV and 33kV substations

 

New Switchboard shelters in Sarir

Installation of MV-LV transformers

 

New Switchboard shelters in Sarir

Installation of new 11kV disconnectors in existing gantry